How the Coalition doomed Inland Rail before Labor killed it

| By Oliver Jacques
Join the conversation
14
aerial shot of track

Several bridges have had to be demolished and rebuilt along the Inland Rail route. Photo: Inland Rail/Facebook.

The federal Labor Government has been accused of abandoning regional communities after ditching the Inland Rail vision of a freight line from Melbourne and Brisbane by halting it at Parkes.

But the uncomfortable truth is Labor had little choice.

By the time it inherited the project, Inland Rail had already become a runaway train – burdened by the wrong route, cost blowouts and an incomplete project plan destined to fail before the first sleeper was laid.

This was a truly bipartisan bungle that has cost taxpayers billions and again exposed a harsh reality: bureaucrats just can’t do nation-building projects.

The original Inland Rail vision was simple and sensible: move freight between Melbourne and Brisbane faster and cheaper, help farmers and manufacturers get goods to capital cities, and take thousands of trucks off our congested highways.

The TV comedy Utopia wrote the script to this drama back in 2014.

In one memorable episode, Rob Sitch’s fictional Nation Building Authority pitches a perfectly sensible Melbourne to Brisbane freight rail project through regional Australia. He explains it stacks up economically, but the politicians are not impressed. Freight trains through sparsely populated rural areas just aren’t sexy. What they really want is something faster, shinier and politically exciting – so the idea gradually morphs into a plan for high-speed passenger rail connecting Melbourne, Sydney and Brisbane.

“I don’t want to build it, I just want to launch it,” Kitty Flanagan’s character famously said.

Art turned into reality the following year when Brisbane-based private consortium National Trunk Rail proposed a $13 billion Melbourne-to-Brisbane freight line via Shepparton, Tocumwal and Narrandera.

READ ALSO Inland rail debacle shows route should have gone through Narrandera, not Wagga

This was a flatter alignment that avoided difficult terrain and major urban disruption while passing directly through some of the nation’s richest food-producing regions – making it accessible to producers across the Riverina.

But the Coalition backed the government-owned Australian Rail Track Corporation’s supposedly cheaper eastern route through the larger population centres of Albury and Wagga. At the time, the line was expected to cost about $10 billion.

That figure now looks more comical than any scene from Utopia.

Today, the cost estimate has exploded to more than $45 billion. It was supposed to be finished by next year, yet not a single track has been laid in Queensland – the most critical section of the route.

Perhaps the biggest irony is that Inland Rail was marketed as a way to help local producers reach global export markets, yet the ATRC line had no plan to reach a port at either end. Rob Sitch couldn’t have dreamt of that script.

An independent review of Inland Rail, led by Dr Kerry Schott, was scathing.

Her report found ARTC suffered from weak governance, poor risk management and unreliable cost and schedule reporting. She concluded that the organisation lacked adequate skills and oversight and failed to resolve key problems that should have been addressed long before billions were committed.

None of this should have surprised anyone.

Former National Trunk Rail chairman Martin Albrecht warned years ago that the ARTC plan would become “the NBN all over again” – a government-run project sold as cheap before becoming vastly more expensive.

The Wagga alignment also brought its own costly headaches – bridge demolitions, traffic disruption and complicated construction through the centre of town – while bypassing much of the Riverina food bowl that Inland Rail was supposedly designed to serve in the first place.

Of course, governments never build these projects alone.

Large infrastructure projects attract armies of consultants, lawyers, planners and contractors, all clipping tickets along the way. Bureaucracies, lacking commercial discipline and often desperate to protect political timetables, become easy prey.

The result is a familiar Australian ritual – lowball the cost, announce the project with fanfare, then return years later asking taxpayers for billions more.

Did anyone seriously expect this federal government to keep spending an infinite amount on the Queensland leg of a project that won’t pass through any Labor seats?

READ ALSO Wagga braces for more pain with less gain as Inland Rail slashed 1000 km short

So yes, Labor has pulled the handbrake.

But the Coalition had already driven the train off the track.

Australians are left with a massive bill, while nobody in power has been held to account.

In the end, both sides of politics have made Utopia look less like satire and more like a documentary.

Free Daily Digest

Want the best Canberra news delivered daily? We package the most-read Canberra stories and send them to your inbox. Sign-up now for trusted local news that will never be behind a paywall.
Loading
By submitting your email address you are agreeing to Region Group's terms and conditions and privacy policy.

Join the conversation

14
All Comments
  • All Comments
  • Website Comments
LatestOldest
kaleen_calous4:22 pm 21 May 26

My oh my what is it with Australia and trains! Nation building is expensive and usually not very sexy. Bottom line is both major political parties only give a damn about national development when it aligns with their sectorial and electoral interests. The trucking companies like things just as they are thank you – diesel and bitumen will always win. And it’s too expensive to justify a few isolated cockies getting their piggies to market. Much better value to upgrade 30 year old subs and pay billions to sub-contract our sovereignty out to AUKUS.

It’s a shame.
We need more freight moved by rail.

It’s a joke and a waste of resources that we move freight between our largest cities by road in 30-60tonne lots.

Never read such a political article in my life but it is Canberra- based and given this publications propensity for picking the left side every time it is hardly surprising. Yet again this is somehow the Conservatives fault when they haven’t been the government controlling the finance and direction of the project for 4 years. That is absolutely laughable considering the same government just ploughed billions more extra dollars into the Victorian ALP Governments tunnel to nowhere. A project that NEVER stacked up economically or in any other way.

To be fair Rob we did see the below piece published a few days ago right here at the RiotAct. It featured a picture of grim Jim and Albo with large Pinocchio-like noses, yes undoubtably noses, on the back of the biggest lies told to voters since, well, probably ever.

Of course there were some very stern appraisals from RiotAct commenters including suggestions of SkyNews job applications and panicked leftist defences of the afforementioned porkies.

But at least now that the polls have turned against the government and Angus Taylor is the preferred Prime Minister we seem to be reading less about 94 seat victories and thumping election wins.

https://region.com.au/promises-made-promises-broken-to-understand-the-budget-read-between-the-lies/966272/

Yes of course. No doubt last week’s budget debacle was the Coalition’s fault too.

And what about the NDIS shocker, that too ? And Blackout Bowen’s catastrophic energy policies, those too ?

Capital Retro9:19 am 21 May 26

And Snowy Hydro 2.0?

Costs have blown out $40 billion but they didn’t pull the plug on it.

Why?

Well to be fair CR that debacle belonged to the lefty masquerading as a conservative. The one who now champions teals, hates the Liberals who made him Prime Minister and arguably started the rot for the Coalition. Though ironically Albo and his brian snap of a budget has reinvigorated things a bit.

Mind you speaking of doomed policies, with the 20 year anniversary of Al Gore’s fictional fairytale did you notice the IPCC are now dialing back all the doomsday scenarios of climate catastrophe. Wonder if anyone in Labor will even be held to account for the huge power price rises and $275 porky pies.

Because if you stop Snowy Hydro at this point, you get absolutely nothing. If you stop inland rail as they plan, you still get the line to Parkes – i.e. some of the benefits are realised.

It’s really not hard to understand. Although I know some minds on here find basic things hard to understand.

Another day, another dribble from penfold. Now pretending an LNP signature policy was a labor policy decision.

Lol.

Penfold instantly avoids the subject then wanders off into the fantasy land inhabited by propagandists bent on tearing the social fabric in favour of wannabe autocrats and their uber-rich paymasters.

Like Trump, he lies interminably, practically every sentence or phrase.

JS9 how wonderful of you to illuminate the conversation with your MENSA-level intellect and wit. Sadly Axon wasn’t able to do likewise.

Whilst you’re correct about inland rail and the line to Parkes, perhaps you might wish to investiage the notion of sunk costs in relation to Malcolm’s Snowy. And cost / benefits. If the crazy think finishes up costing $40 billion as some predict and it delivers only enough stored power to keep a light bulb on for 20 minutes then we’d be best to down tools right now and walk away.

But such economic and cashflow considerations probably only trouble we mere mortals. Btw Labor have been in power for four disastrous years now, they get to own these decisions.

Out of curiosity, wonder how many nuclear plants we could get for $40 billion. We could get 20 SMRs. That’s power to a lot of light bulbs.

Btw JS9 a little research reveals that the route for inland rail was set in 2010. A little further research might reveal who was in government then, though as a hint it wasn’t the Coalition.

We already had rail links for Melbourne->Adelaide & Melbourne->Sydney (&vice versa); the plan was to extend the Melbourne->Brisbane link so that amongst other things Parkes could be used as a switching point from Brisbane onto the Broken Hill line to Adelaide & Perth, or onto/from the Sydney Main West Line at Narromine or to do things like ship coal to Newcastle via the Main North Line at Narrabri.

From a railfreight perspective, sending from Melbourne bound for Sydney via Parkes makes no sense, as its an extra 3 or 4 hrs worth of detour to arrive at its primary destination on track that sees an average speed of 40kph (the Sydney-Broken Hill Line).
Sending railfreight from Melbourne->Parkes->Crystal Brook->Adelaide takes ten plus extra hours instead of using the existing Melbourne->Horsham->Murray Bridge->Adelaide.

And the StockingbingalNarromine\Dubbo Branch line doesn’t & won’t see any kind of large volume of cargo without Inland Rail connecting through Narrabri and on to the QLD Border.

For more geography & rail maps (with tonnage and average section speeds), please see https://spatial.infrastructure.gov.au/portal/apps/webappviewer/index.html?id=fcd0db38b04a430f9f8ea9479d91cb4f,

Capital Retro7:09 am 22 May 26

Good comment.

Whatever the outcome heavy trucks will still be needed at the start and destination to deliver goods to wholesale/retail distribution points. The exception is where rail goes directly to port like Port Botany in NSW.

Currently, transporting goods for Australian consumption are done point to point by road transport to avoid double handling and extra time if rail is used.