Some parts of the light rail stage 2A construction works are months ahead of schedule. Photo: Ian Bushnell.
Light rail stage 2A construction is full steam ahead with the partial reopening of London Circuit East expected 10 months ahead of schedule.
But early milestones appear to be cold comfort to the City’s small businesses, with one mainstay labelling the project’s timeline a “death sentence”.
Transport Minister Chris Steel’s update on construction revealed that the January blitz provided “significant momentum” and saw works completed along Northbourne Avenue between Vernon Circle and Cooyong Street, including at the Alinga Street intersection and light rail stop.
“This busy period which, although disruptive in the short term, avoids up to 30 separate weekend closures,” he said.
Mr Steel said the sequenced construction staging was allowing disruption to be kept “as low as reasonably possible” and to find efficiencies where feasible.
Examples included prioritising completing work at the Bailey’s Corner loading zone – allowing the temporary loading zone in the Theatre Lane carpark to be converted back to additional parking spaces – and modifying the schedule to speed up construction of the public realm precinct in front of the Sydney and Melbourne Buildings, which should be finalised mid this year.
“This means access to private land in these areas is now required for shorter periods of time, and will allow construction fencing to be moved from the colonnades of both buildings to the outside, opening up a wider public realm … as soon as paving works are complete,” Mr Steel said.
“These accelerated works will also enable the partial reopening of London Circuit East to general traffic, now expected from quarter 3 this year, 10 months earlier than originally scheduled.”
Mr Steel advised that the new Parkes Way Bridge was ready for light rail tracks to be installed.
“Construction of all stops and rail alignment, including new landscaping and street amenities, [is] expected to be substantially complete later this year … and major construction on-site activities are on track for completion by early 2027,” he said.
“Canberrans can expect a staged reopening of roads and verges throughout the year ahead of new light rail services to Commonwealth Park commencing in 2028.”
Mr Steel also touched on how the government had been trying to support businesses during the construction period.
This included expanding the Business Partnership Plan, waiving outdoor dining permit fees for businesses directly impacted by construction activities, reducing liquor licence fees, business activation grants, and micro-grants for multicultural-themed activities during the National Multicultural Festival.
Additional lighting and more fence screening, free parking on Wednesday to Sunday from 5:30 pm, free public transport trials, six new dedicated rideshare pick-up and drop-off points in the City, and providing way-finding maps for businesses to share with clients have also been ACT Government initiatives.
It’s also been suggested that local businesses drop off takeaway menus and business cards at construction sites and offices to encourage workers to spend locally.

Bar Rochford owner Nick Smith with Minister Tara Cheyne and Chief Minister during the 2024 election campaign. Photo: Ian Bushnell.
One business owner has taken to social media to explain why this isn’t enough.
Bar Rochford’s Nick Smith wrote that the wine and cocktail bar has only broken even once in the past eight weeks.
“So how sustainable is running a business on London Cct at present and into 2027, 2028, 2029?” he asked.
“Since January 2025, we have received a $5000 Music Grant, $4000 off our annual Liquor Licence and 15 Free Parking Tickets to pass onto our customers from the ACT Government. Nothing else.
“How can a three-year, multi-million dollar government project not even consider 0.5 per cent of the Light Rail Budget to support the small businesses already affected on this strip?”
Mr Smith went on to question why the government had also sold and decommissioned both the large carparks next to the Sydney and Melbourne Buildings at the same time construction was occurring, resulting in the venue feeling “completely cut off from society”.
“Businesses should expect to have to deal with government projects and upgrades,” he wrote.
“Six to 12 months is OK, but 36 months is a death sentence for small businesses.”
Opposition Leader Mark Parton and Kurrajong independent MLA Thomas Emerson picked up these points.
Mr Parton questioned why Mr Steel didn’t share the feedback he’d been receiving from businesses as part of the light rail update.
“I’m not surprised, as I’m sure much of that feedback would’ve been laced with words that [the Speaker] would consider non-parliamentary,” he said.
City and Night-time Economy Minister Tara Cheyne defended the government’s decisions, especially for scheduling the construction blitz during the summer holidays.
She acknowledged it was a “major, major disruption”, but it had also been “logical”.
“It could have been much worse, and we have made some hard decisions to avoid something that really would have had a huge impact on our venues in the City,” Ms Cheyne said.
“It’s not like the City is closed.”
Ms Cheyne announced Music ACT would be receiving a one-off donation of $20,000 to further enable and promote live music, and that plenty of special event declarations were coming up, meaning businesses can automatically stay open until 2 am.
These include for this weekend’s Canberra Comedy Festival and next month’s National Folk Festival.
She also encouraged patrons to spend locally, echoing Mr Smith’s sentiments: “If you want to see some of the independent Canberran venues like Rochford still be here in 2027, please continue to support city businesses and spread the word.”