Homelessness Minister Yvette Berry has asked for a review of procurement processes after the Woden Youth Foyer sat empty for months. Photo: Michelle Kroll.
The Canberra Liberals have demanded answers about why 20 purpose-built units to tackle homelessness sat empty despite being certified nearly a year ago.
The units at the Woden Youth Foyer, located at the CIT campus in Phillip, were designed to be accessed by young people aged 16 to 24 years. Three of the units will accommodate young parents.
It’s an Education First Youth (EFY) Foyer that not only provides supported, private housing but also dedicated coaching, access to education, training and employment pathways, and communal spaces for workshops, study and social activities.
Despite receiving its Certificate of Occupancy on 16 May 2025 and reaching Conditional Practical Completion on 4 June 2025, no one has moved in.
“The government’s own answers confirm this building was certified for occupation in May and practically complete in June last year,” Shadow Community and Government Services Minister Peter Cain said.
“What changed between May 2025, when the building was certified for occupation, and early 2026, when it remained empty?
“You cannot have a building certified for use, declared complete on your own website, and still sitting empty nearly a year later while vulnerable young people are being turned away.”
The ACT Government’s Built for CBR website labelled the project complete in July 2025.
Mr Cain questioned why, despite the certificate of occupancy, the facility was still unoccupied.
“By September, construction was complete and the tender had already closed, yet the Assembly was only told procurement was underway,” he said.
“This facility sat empty through winter while young people were sleeping rough.”
In response to questions on notice, Homelessness Minister Yvette Berry confirmed that occupation wasn’t possible due to “ongoing rectification of defects”, including changes to fire exit management, repairs to walls and doors, and bathroom repairs.
“The decision was made to address these defects prior to students moving into the foyer to limit disruption,” she wrote.
“The extended time for fixing these issues was, in part, due to the focus on remediation of defects within the CIT buildings due to the need for it to be operational at the start of Semester 2, 2025.”
A tender for a supplier was released in July 2025 and was open for a month. A contract with the successful preferred supplier was executed on 30 January 2026.
That organisation is Marymead CatholicCare Group, which has been working with the Brotherhood of St Laurence to recruit and train staff. It’s also liaising with CIT to deliver a Certificate I in Developing Independence in the foyer.

The Woden Youth Foyer is co-located at CIT’s southside campus. Photo: Canberra Institute of Technology.
Shadow Social Housing and Homelessness Minister Chiaka Barry said the situation once again raised questions about the ACT Government’s procurement processes.
“If procurement dragged on for five months after the tender closed, the minister needs to explain why. And if the defects were so serious that they delayed occupation, the minister needs to explain how a Certificate of Occupancy was ever issued in the first place,” she said.
“Again, this Labor Government has demonstrated their inability to manage procurement, providing unreliable timelines and shady explanations, while failing to prioritise the delivery of critical services when they are most needed.”
A response from the Health and Community Services Directorate outlined that a certificate of occupancy didn’t mean doors could be opened straight away.
“It is important to note that a certificate of occupancy is a milestone and does not, in itself, always indicate that a building is ready to be occupied, especially with vulnerable young people,” a statement outlined.
“It is also important to recognise that the procurement of goods and services takes time and must be undertaken properly.”
The Health and Community Services Directorate’s statement detailed that procurement planning began in November 2024 and that the matter was considered by the Government Procurement Board in April 2025. Approval was given two months later, and the tender was released on 15 July 2025.
“Securing a preferred supplier took approximately five months, reflecting the need to undertake a rigorous and proportionate procurement process. This included detailed evaluation of submissions, contract negotiations as well as appropriate approvals and probity checks,” it outlined.
“Procurement timelines can vary depending on factors such as risk, complexity, market capability, approval requirements, and contract negotiations, particularly for specialist services supporting vulnerable young people.”
The Health and Community Services Directorate’s response stated that it shouldn’t be expected that a supplier would have a full complement of trained staff if it secured work.
It also confirmed the outstanding defects in the Youth Foyer were “non-critical” and would be completed by December.
In light of the situation, Ms Berry said processes would be reviewed.
“As new housing and accommodation is built, ensuring that these spaces are safe and comfortable for people to call home is a priority,” she said.
“I acknowledge that, in this case, procurement processes to appoint a service provider took too long. I have asked the directorate to review their processes so this doesn’t happen again.
“I look forward to welcoming the team at Marymead CatholicCare and the young people who will call the Foyer home.”
A Marymead CatholicCare spokesperson confirmed that staff had been recruited and that referrals had been received from potential students.
It’s expected that the first residents will move in sometime in the next two weeks.