New track in London Circuit. More will be laid across the Edinburgh Avenue intersection. Photo: Ian Bushnell.
Construction on light rail Stage 2A is ramping up in the second half of this year, with new track being laid, stops being completed, and new streetscapes being created.
But Infrastructure Canberra says the next stage of works will also come with more traffic disruptions and detours.
The agency has issued its latest update highlighting the installation of rail across the intersection of London Circuit and Commonwealth Avenue, and the installation of the final canopy at the Commonwealth Park and City South stops.
Track slab and rail installation works will also be underway at the London Circuit-Edinburgh Avenue intersection from mid-July to August.
Works to lay track across the intersection will start next week.
Construction crews will need to close the intersection on specific dates overnight and redirect westbound traffic on Edinburgh Avenue in the coming weeks to ensure the rail infrastructure can be safely installed.
To safely set up the new works, the intersection between The Mews and Knowles Place will be closed from 8 pm to 5 am overnight on Sunday, 12 July, Sunday, 26 July, and Sunday, 9 August.
From 5 am on Monday, 13 July, traffic on Edinburgh Avenue will be one-way westbound between Knowles Place and Marcus Clarke Street until 5 am on Monday, 10 August. Detours will be in place.
Rail will be installed in stages across the intersection, first on the closed intersection lanes closest to the Metropolitan Building between 13 and 26 July while traffic is redirected to the lanes closer to the QT side of the intersection.
Traffic will then be switched to the lanes closest to the Metropolitan building from 27 July to 9 August while rails are installed on the closed lanes closer to the QT side of the intersection.
Infrastructure Canberra says staged works will intensify on London Circuit East from mid-July to enable the partial reopening of the road to vehicles later this year.
This will require temporary lane closures between Baileys Arcade and Ainslie Place from 13 July for up to three months.
Crews will install new kerbs and footpaths and carry out stormwater upgrades to increase the drainage system capacity and futureproof against flooding.
Infrastructure Canberra says the works will be carried out in stages to reduce the impact on the community.
New accessible pedestrian verges on London Circuit in front of the Sydney and Melbourne buildings are now open for use.
Infrastructure Canberra says these new verges are wider, safer and fully accessible, designed to support all users, including people with mobility aids and prams.
“The reopening of the verges will make it easier to move through the city and provide more access to businesses in the area,” Infrastructure Canberra said.
“Businesses will also be able to take advantage of the upgrades by using the newly created spaces for outdoor dining.”
The light rail project includes significant improvements to the public realm along its route, including new footpaths, bike lanes, trees and landscaping.
Infrastructure Canberra says intermittent road and lane closures will also be in place across Northbourne Avenue, Parkes Way and Commonwealth Avenue during July and August to support essential works.