Transport Minister Chris Steel at the almost completed Woden Interchange, which opens on 20 April. Photo: Ian Bushnell.
It’s light and airy, and the timber-panelled platform roofs look a treat, but will the new Woden Interchange do enough to protect passengers from Canberra’s notorious weather extremes?
The ACT Government has perhaps prematurely announced the project’s completion, even though it still looks like a construction site, but the new interchange will take its first buses from 20 April.
Until then, workers will be putting the final touches on the interchange and doing commissioning and testing work.
Transport Minister Chris Steel, accompanied by local Labor MLA Marisa Patterson, took the media on a first look at the light-rail-enabled facility.
Mr Steel said the previous interchange was dark, hidden away and passengers felt unsafe.
He said the new interchange was designed to be open, welcoming and safe, as well as integrated with the broader precinct renewal in Woden.
“We’ve incorporated some of the same design elements for the high-quality shelters that have been built as part of a light rail Stage 1 and Stage 2A into the design of the Woden Interchange, so that there is that design symmetry, for not just the light rail stops but the bus shelters as well,” he said.
“When we consulted the community on the design of the Woden Interchange project, we heard from them that they wanted some extended shelter infrastructure, and so we’ve built that into the final design, and we’ve constructed it.”
Mr Steel said it included an extended shelter outside the CIT campus, as well as shelter at the crossing points, so that when people were waiting to cross the interchange, they would have it available to them.
“We’ve now opened up the interchange, it’s got far better solar access, it’s got modern shelter, and it’s got those opportunities for people to access it from varying parts of the Town Centre,” he said.





There would also be minor works to improve the verge just outside Grand Central Towers, which would allow a new north-south connection between Bradley Street and Bowe Street.
This would provide a drop-off point for people wanting to access the new interchange and Woden Westfield, particularly for those with mobility issues, and enable deliveries to local businesses.
Mr Steel said the interchange was the largest public investment in Woden for 50 years. However, because it is embedded in the $375 million CIT project, he could not provide a cost figure specifically for it.
An extra $17.5 million was required to address unforeseen utility works on Callam Street, but these would now benefit the Town Centre for decades to come.
Mr Steel said that as the new platform comes online, bus operations would cease at the current interim temporary bus interchange on the Matilda Street carpark, which will be the site of Hellenic Club’s Woden Village mixed-use development.
The new light rail-ready stops in the middle of the interchange would service Rapid bus services, particularly R5 and R4, until light rail came to Woden.
The interchange also includes new trees and landscaping, upgraded cycling and pedestrian paths, and secure bike and e-scooter storage.