The simple reason this expert says Canberra’s road upgrades take so long

| By James Coleman
Join the conversation
44
group of politicians sod turning

ACT City Minister Tara Cheyne, Ginninderra ACT Labor MLA Yvette Berry, Federal Transport Minister Catherine King and Fenner MP Andrew Leigh turning the sod on William Hovell Drive. Photo: ACT Government.

A generation of Canberrans has nearly finished school in the time it’s taken to get construction under way on the duplication of William Hovell Drive.

Ten years after ACT Labor promised to duplicate the final 4.5 km stretch between Drake Brockman Drive and John Gorton Drive before the 2016 election, major works have finally begun on the Belconnen road.

But even now, the project isn’t expected to finish until late 2028.

Further south, Tuggeranong residents are still waiting for construction to start on the duplication of Athllon Drive – a project first pitched by former Liberal senator Zed Seselja.

So why is it taking more than a decade to duplicate less than five kilometres of road?

The ACT Government points to environmental approvals, planning processes and procurement hurdles. But infrastructure experts say the answer is much simpler: governments are choosing not to prioritise the work.

William Hovell Drive duplication render

A render of the completed William Hovell Drive duplication. Photo: ACT Government.

Remind me of the timelines here

The William Hovell Drive duplication was first announced in 2016 as an ACT Labor election commitment.

Initial feasibility funding followed in the 2018-19 ACT Budget. Then the project was recommitted in the 2020 election campaign before the ACT and federal governments locked in a combined $107.25 million funding package in 2021-22.

Construction officially started this week.

Once complete, the road will have two lanes in each direction between John Gorton Drive and Drake Brockman Drive, alongside new walking and cycling infrastructure, a signalised intersection and wildlife crossings.

The ACT Government says the project will “improve safety, ease congestion and support growth in Canberra’s north-western suburbs” for the more than 20,000 vehicles using the corridor every day.

Lovely. But timelines have repeatedly blown out.

READ ALSO $50 million from the Feds to help in 'easing congestion' on ACT roads

In 2023, the project was expected to open in late 2026. It’s now forecast for completion in late 2028 or early 2029.

A government spokesperson blamed “extensive environmental and planning approvals under both ACT and Commonwealth legislation”.

“The development of these plans involved extensive consultation with both agencies and multiple rounds of revision to address detailed feedback and meet all regulatory and environmental requirements,” the spokesperson told Region.

For Athllon Drive, the government previously said there had been a “number of steps” before construction could begin, including “feasibility studies, concept, preliminary and final design and various stages of procurement”.

Signs reading “We are duplicating this road” were installed along Athllon Drive in 2020, but development approval was only granted in March this year.

sign on Athllon Drive

These signs were installed along Athllon Drive in 2020. Photo: David Murtagh.

National Transport Research Organisation CEO Michael Caltabiano said decade-long waits for major road projects were not normal.

“No, it’s not normal to be waiting a decade or more for the delivery of really important infrastructure to keep Canberra connected,” he told Region.

“What the community’s also saying is that you can’t just put a sign up on Athllon Drive and leave it there for six years and say it’s coming. You actually need to deliver.”

So, what’s happening?

Mr Caltabiano rejected suggestions that environmental protections or industry-wide issues were primarily responsible for the delays.

“No, not to my knowledge,” he said when asked whether additional regulations were slowing projects down.

Instead, he said governments were making conscious funding and priority decisions.

“It’s purely a policy position of governments,” he said.

“These are really important upgrades for the ACT. They’ve been long overdue and it’s government that must decide where to prioritise the funding for them.”

READ ALSO It's been a decade but Athllon Drive Duplication in sight with DA approved

He said Canberra’s rapid population growth made projects like William Hovell and Athllon drives increasingly important.

“We must have Athlon Drive duplicated. We must have William Hovel Drive duplicated. We must have these really important links in the transport system functional.”

At the same time, the delays are making projects more expensive.

“There’s been massive cost escalation across the infrastructure sector over the last decade,” Mr Caltabiano said, pointing to labour shortages, productivity issues and rising material costs.

“The longer these pieces of infrastructure take to deliver, the more expensive they become per lineal meter, per lane, per kilometre.”

Is duplication really the answer to congestion?

The projects also sit at the centre of a broader debate over whether duplicating roads actually fixes congestion.

Transport experts such as Institute for Sensible Transport director Elliot Fishman have previously argued road widening creates “induced demand”, where extra capacity simply attracts more traffic.

“You end up getting four lanes of congested traffic instead of two,” Dr Fishman recently told ABC Canberra.

An artist's impression of the Atkins Street/Langdon Avenue intersection looking south towards Tuggeranong Town Centre

An artist’s impression of the Atkins Street/Langdon Avenue intersection on Athllon Drive. Photo: ACT Government.

But Mr Caltabiano strongly disagrees.

“You can’t clog the arteries of the system and then expect the city and the territory to function,” he said.

“The planning’s been long completed for these key linkages and they’ve been deemed to be required to ensure that communities are connected in an efficient way.”

He said comparisons with massive 23-lane American-style freeways missed the mark in Canberra’s case.

“These analogies are predominantly coming out of the US when they’re widening freeways that are already 23 lanes wide, instead of reimagining how people and freight move.

“But arguments about how the more lanes you build, the more traffic you get, are completely nonsensical in this environment.”

Free Daily Digest

Want the best Canberra news delivered daily? We package the most-read Canberra stories and send them to your inbox. Sign-up now for trusted local news that will never be behind a paywall.
Loading
By submitting your email address you are agreeing to Region Group's terms and conditions and privacy policy.

Join the conversation

44
All Comments
  • All Comments
  • Website Comments
LatestOldest

Bogus contracts filter money to “friends”. Every single politician is a waste of space. Nothing but constant lies and bullsh!t. As long as they magically become rich “doing the right thing” you mean nothing. Name one politician that has done anything for the people and made change in the last 20 years and sticks out in everyone’s mind? Name one, you can’t.

I hope they do a complete job of it this time (when the eventually get started), unlike Ashley Drive that still isn’t duplicated between Johnson Drive and Clift Crescent. We should have been suspicious when they agreed to extend the duplication “all the way *TO* Johnson Dr” – what they didn’t say was that they would fail to duplicate the return journey.

Gregg Heldon11:36 pm 01 Jun 26

Because the Government doesn’t care about you if you don’t live in the inner north. If you live there, you matter. If you don’t, you are considered third rate.

Bill Gemmell5:16 pm 31 May 26

I merely note that not one of these roads projects is supported by a comprehensive business case.
Oh yes, I note some one has had a poke at the Molonglo Bridge Project. I suggest they have a broader think about why a strategic link in and out of Molonglo suburbs is of importance, especially before engaging gheir keyboard.

Bennett Bennett5:11 pm 31 May 26

Seems extremely easy to narrow all the suburban streets, put speed humps and squeeze bike lanes into them. Absolute life changing spend and I feel much safer now. It was a real problem before.

No suprises here. Politicians hard at work, doing the only things they know

The Drake Walker6:23 am 31 May 26

There are several reasons why the Drake Brockman Drive upgrade has been delayed over the years. A major , more recent reason was the botched intersection designs that took until at least early 2025 to resolve having been rejected in the DA for Stage 2 of March 2024. See the innuendo in https://share.google/JNZWwD03yVdHcrd6e
The people continue to suffer, notable groups being residents still without their access road, motorists turning onto or from The Drake and those crossing The Drake.

The Drake Walker2:57 am 31 May 26

I agree.

“Ten years after ACT Labor promised to duplicate the final 4.5 km stretch between Drake Brockman Drive and John Gorton Drive before the 2016 election, major works have finally begun on the Belconnen road”.

There’s been plenty of work!

Signs were erected at each end after the announcement in 2016. They were replaced before the 2020 election, and AGAIN before the 2024 election. That’s THREE sets of signs. It’s not like nothings’ been happening.

Im sure someone was hired specifically for those signs and someone had to hire them.

And what did they cost.

Induced demand does not occur 100% of the time. The way anti-car advocates rely on it every time is rather annoying.

This duplication should have occurred before people moved into Ginninderry, along with Drake-Brockman.

Robert Fisher3:57 pm 30 May 26

It’s the usual cry of stop spending money on things that don’t directly benefit me and reduce the debt. But if it is something that I like and benefit from, then money is no object.

A piccy of Cheyne, Berry, King & bloody Leigh on the shovels before having coffee & croissants doesn’t instil enthusiasm.

It’s all about the spin. First the loud public announcement. Ages later something might start but it won’t get finished as there’s lots of announcements, lots of starts but no desire to actually finish the work because they want to look like they’re actually doing something instead of just talking about it. Canberra is always a mess of orange plastic, signs & barriers.

chrisjeanemery12:53 pm 30 May 26

But we are getting a slow tram to replace rapid buses.

The Labor party is a slow, meandering sloth. University -> union organiser ->activist -> staffer -> politician. Sorry sloths

Most of Athllon was duplicated already. The bits along mawson and Tuggeranong were done decades ago.

Yet we now get bike paths as if that suddenly makes it easier to get to work on the other side of town.

The government is out of touch but still does just enough that rusted on Labor believe they’re doing their best.

Rhonda from Utopia explained the primary concern is all the publicity and photo opportunities derived from over a decade of “announceables”, actually getting in and getting the job done is just a secondary concern.

The ACT Local Council can get away with these delays as they are elected again and again and never held to account.

Yes. Canberra. Labourland. Sheep keep voting Labour whatever they do …. massochistic, really. And dumb.

And will be again with rudderless Libs, Green & Independent wannabes opposition.

Daily Digest

Want the best Canberra news delivered daily? Every day we package the most popular Region Canberra stories and send them straight to your inbox. Sign-up now for trusted local news that will never be behind a paywall.

By submitting your email address you are agreeing to Region Group's terms and conditions and privacy policy.