16 April 2025

Big crane ready to do heavy lifting at Molonglo bridge works, road closure warning

| Ian Bushnell
Join the conversation
8

It’s a big crane for a big job. It will lift 160-tonne steel girders into place across the Molonglo River. Photo: Ryan Hemsley.

The big crane is up at the Molonglo River Bridge site at Coppins Crossing, ready to lift 20 steel girders transported from Newcastle into place from 28 April.

The job will take up to three weeks and Coppins Crossing Road will close from 5 am on 28 April, reopening on or before 17 May 2025.

The girders weigh 160 tonnes, are 70-metres long and 5.36-metres high.

Coppins Crossing Road will close between Holborow Avenue and Hazel Hawke Avenue today (17 April) from 10 am to 3 pm to enable the safe transfer of the girder transport system across the river.

READ ALSO Aldi confirms opening date for long-awaited Wright supermarket

During the long closure, the northern side girders will be lifted into place. The southern side steel girders can be lifted safely without closing Coppins Crossing Road.

The lift requires the second-biggest crane in Australia, taller than Black Mountain Tower, according to City and Government Services Minister Tara Cheyne.

Ms Cheyne said the girder job would be a significant milestone for the Molonglo River Bridge, but a project of this size requires the area to be closed for a period of time.

“This has been years in the making and months and months of planning,” she said.

“It’s unavoidable and it’s inevitable that we have to make this closure. We’ve tried to give as much time as possible so that people can prepare.”

Ms Cheyne said the sheer scale and logistics of the operation meant that it could not be aligned with school holidays to minimise disruption.

A viewing platform has been provided to safely watch the crane in action. To access the platform, park at the Namarag Reserve car park off Thancoupie Crescent and follow signs to a designated viewing area. To stay safe, do not go beyond barriers, slow down or stop on Coppins Crossing Road.

Molonglo River Bridge

Smoother, faster, safer: What the complete Molonglo River Bridge will look like. Photo: ACT Government.

Infrastructure Canberra said the closure would ensure the safety of road users, the public, and other personnel on and around the project site.

Motorists are asked to use these detours:

  • Southbound from Belconnen – from William Hovell Drive, take the off-ramp to Parkes Way and merge onto Tuggeranong Parkway.
  • Northbound from Molonglo Valley – from John Gorton Drive turn onto Cotter Road then follow the ramp onto Tuggeranong Parkway and take the left exit at Glenloch interchange to merge onto William Hovell Drive.

Commuters are also urged to rethink their routine and consider travelling earlier or later to avoid peak times and allow for additional travel time.

Public transport will also be affected.

Bus Route 47 will not service Denman Prospect during the closure and will only service stops between Belconnen and Whitlam.

Dedicated school services will continue to operate as normal from Denman Prospect. However, students who usually connect with Route 47 in Denman Prospect will need to arrange alternative travel options to access their school services.

Students attending Evelyn Scott School via the Route 47 temporary school-only service may arrive after the morning school bell. The afternoon school-only service is also expected to experience some delays for the return journey after departing from Evelyn Scott School.

READ ALSO ACT Auditor-General to examine Phillip Pool planning changes

The new bridge will span 200 metres across the Molonglo Nature Reserve and river, and combined with 1.7 km of new arterial roads and two new intersections, it will provide smooth, safe and faster access to the future Molonglo Town Centre from the suburb of Whitlam and future northern Molonglo Valley suburbs.

It will also deliver a long-awaited dependable link between Belconnen and Canberra’s south.

The works include off-road shared paths and a pedestrian underpass to encourage more Canberrans to ride or walk.

To stay up to date on the impacts, visit the Built for CBR website.

Free Daily Digest

Want the best Canberra news delivered daily? We package the most-read Canberra stories and send them to your inbox. Sign-up now for trusted local news that will never be behind a paywall.
Loading
By submitting your email address you are agreeing to Region Group's terms and conditions and privacy policy.

Join the conversation

8
All Comments
  • All Comments
  • Website Comments
LatestOldest

I suppose both sides of this one will line up.

I hope this bridge has been designed to take the future light rail and does not require future work to make it rail ready

A public transport group sought and were given assurance that space would be included in the design. The problem now is to guard against the takeover/theft of that space for general traffic, like what has occurred in Adelaide Ave. .

Capital Retro9:08 am 18 Apr 25

The grades are too steep for a tram.

What is the ‘ruling’ grade at the bridge that makes it too steep? Your comment needs some factual justification considering the ACT Government has made provision.

Capital Retro8:54 am 21 Apr 25

Roger s, you are correct but I don’t think either of us will be around to see it and the Territory will be well and truly busted financially by then anyhow.
Here is the blurb in the initial report which was made 7 years ago:
4.2.4 Light Rail To accommodate the efficient operation of the future light rail, the vertical grade of JGD3C must be less than 5% as defined by Transport Canberra Light Rail (TCLR). From a horizontal alignment perspective, a 12m median is required to accommodate light rail to travel in each direction. This width is fixed and cannot be reduced. Following a meeting with TCLR at the initial stage of the PSP design it was confirmed that there are no further updates required to the JGD3B Future Light Rail Design Criteria memo (August 2018), based on the available information to date. The 12m reserve has been agreed with TCLR and has been accommodated within the JGD3C PSP design. The JGD3B Future Light Rail Design Criteria Memo can be viewed in Appendix A. Each intersection along the JGD3C main carriageway has right-turn lanes inside the 12m median. These right-turn lanes will need to be either removed or relocated if light rail is to be constructed in the future. This design approach 10 IA216800.-RP-RD-125_RevA_Final PSP Design Report Preliminary Sketch Plan Design Report was approved by TCCS and Roads ACT in a meeting on Wednesday 31 October 2019. More information about the provision of these intersections can be found in section 4.8 of this design report. There are significant restrictions on widening the road corridor at both the MTC and Whitlam intersections for the future provision of light rail to reduce the impact on these collector roads during light rail construction in approximately 20 years’ time. This is due to the fixed constraints of JGD2A (operational), Whitlam (construction planned from September 2020) and blah blah….”

Capital Retro8:38 am 17 Apr 25

“To stay up to date on the impacts……”
Given the previous experience with bridge collapses in the ACT, is “impact” the right word to use?
https://region.com.au/gde-collapses-onto-barton-highway/26041/

Daily Digest

Want the best Canberra news delivered daily? Every day we package the most popular Region Canberra stories and send them straight to your inbox. Sign-up now for trusted local news that will never be behind a paywall.

By submitting your email address you are agreeing to Region Group's terms and conditions and privacy policy.